log home
  photos
  virtual tour
home
  about us
  daly clan
  colorado
rving
  journal
  our rv
jen & ben
kevin
juice plus+
click here to go to the Photo Album and see a larger image


Log Home

 
Project
 
"Time-line"

July 2001

Take a Virtual Tour
July 2
Instead of 7am, the backhoe and gravel arrived at 9:30. Then it took over 2 hours to set up the crane and widen the driveway to allow the 18-wheeler to back in far enough for the crane to reach the walls on the front of the trailer. Sadly, two more trees had to be sacrificed to get these heavy walls to the site.
Finally, at "high noon", we watched the first wall lifted off and into place. Progress was slow, so by day's end we had only the 4-footers in place across the back of the foundation.

July 3
Today we moved into our neighbors' house across the road (Ken & Kathy Beckwith)Our neighbors house - the Beckwiths - "home" for 10 days, where we'll be house/dog/cat-sitting for 10 days. My commute will be short for a while and I can keep a close eye on progress, "helping" where necessary. The big 10-footers are now in place, though the last one was tough to connect to the very first 4 foot wall, and needed prolonged and painstaking movement with a set of "jaws". What a difference 2 days make: we now have the beginnings of a house instead of a potential swimming pool. What a relief!

Tomorrow is July 4th - Happy Independence Day, America! On Thursday the plumber should arrive to start work. The rest of the Superior wall-setting should take place on Friday.

July 6
"What a difference 2 days make" indeed! On Tuesday the Superior guys joked about taking a 5-day weekend - but they weren't joking! At 4pm on Thursday three guys turned up and removed the crane. This did not bode well, so I called everyone, but could find no-one in at Superior or my builder. Today, Friday, the site was dead, and again no-one would return my calls.

Sacha - 16 - with her lead in her favorite place!To cap it all this morning our 16-year old dog, Sacha - wonderful family pet and friend - wandered off and hasn't been seen since; we spent most of the day searching by foot, bike, car and phone. Suddenly our house building frustrations seem remarkably unimportant!

July 9
First the good news ... Sacha found her way to a house about 3/4 mile away (as the crow flies, but she probably walked much further) and in through their dog door. She couldn't get out, so when the owners returned about 11:30pm (!!!) on Friday, they had an extra dog. I fetched her at midnight - and we were all mightily relieved!

Today, Monday, there was again no sign of Superior, but after much discussion our plumbers (John and Tony) did lay PVC pipe in the gravel sub-floor - about 3-4 hours' work. Now we await word from Superior. Once again we are at a stand-still.

July 10
It seems Superior "ran into a design problem" last Tuesday with the 4' step down from the Laundry to the Mud Room - their foundation drawings were wrong?! It's taken them a week to come up with a solution ... they start pouring some new walls today. The walls will be ready by Thursday, but does that mean they will be installed on Thursday?! And why did no-one communicate the problem to our builder or me?!

July 11, 12, 13 ...
Waiting, waiting!! Thursday came and went (2 weeks since they appeared on site, 2 weeks late, to do a 2-day job), so did Friday! Would I ever choose "Superior" walls again?!!!!!

July 16
Superior were back on site today ... but not for long. They left when they saw that the extra gravel, which they say they requested 2 weeks ago, was not in place ... the builder says he knew nothing of this! Hey, ho ......  "C-o-m-m-u-n-i-c-a-t-i-o-n" seems to be lacking again. It's now two months since we broke ground ....!

July 17
Our excavator came back with a small earth-mover to add more gravel between house and garage. Tomorrow?!

July 18
Good news: Superior were back ... Bad news: they left again. Problems with the gravel (wrong again?!), the crane setting-up, and more confusion over how to set the garage walls. Tomorrow the excavator will be back and MAYBE we'll see Superior back on Friday?!?

July 27
Which Friday?!? Another week of delays and almost zero progress. It took forever to backfill the walk-out basement walls, then to re-prepare the gravel base for the remaining Superior walls, with one rain delay and more mistakes to be corrected. It's now 22 days since the last Superior walls were installed. Superior are now "expected" on Monday, to finish the job they started on June 29th.

In addition, it came to light that a late change to the height of the Superior walls (from 8' to 10') was not matched by a deep enough excavation. So, because we cannot go any higher with the roof, the first floor now has to be "hung" instead of built on top of the Superior walls! Unbelievable!

July 30-31
Well, Superior are back, still scratching heads but making progress, slowly! July 31st is our 30th Wedding Anniversary, so we headed to Edwards for a celebration dinner with Kevin, Ben and Jennifer, test driving a Land Rover (English!) at the same time!

~~~~~~~~~~~~~~~~~~~~~~

Come back soon to check on our progress (and if you're so inclined, say a little prayer on our behalf!)

God bless,
    

archived project timelines

 

archived photo albums
Project Timeline
 
Photo Album
June
 
June
July
 
July
August
 
August
September
 
September
October
 
October
November
 
November
December
 
December
January
 
January
February
 
February
March
 
March
April
 
April
May
 
May
2002
 
2002
Current
 
Current